We started this job at 730 am on 6/3/09 and finished 11 am on 6/4/09. The floor was rotted so we removed a section of the plywood subfloor and replaced it and performed a minor plumbing repair to insure the leak was fixed. You may notice the carpet meets the tile flush with a nice finished edge and we always use the manufactures reccomended subfloor in this case 1/4" Durock mudded to the plywood floor. This project was completed in less than 2 days and for under $600. If you need similar work done please call 615 799 9979 enjoy the pictures Mario is in one.